1: Installation process
insulation test → street light installation → electrical equipment installation → test, withstand voltage test → self-inspection completion acceptance electrical system, follow the civil construction sequence, do a good job of concealed cable pre-buried pipe, and do a good job of blocking the pre-buried pipe.
2: Select the installation location
choose a suitable installation location to facilitate the foundation and installation of the street light pole. 注意不要選擇潮濕的地方,防止路燈桿不穩.
3: Insulation test
使用兆歐表遠程測量線路間及對地絕緣電阻, 檢查電纜是否完好, 是否有滲漏, 和所有測試值 ??應符合規範要求. 遙測完成後, 芯線應接地並放電, 電纜端部用橡皮套密封,然後用膠帶纏繞.
4: Street light installation
安裝高度 (光源到地面), 仰角, 同一地點的路燈照明方向應一致.
5: The longitudinal center line of the lamp installation should be consistent with the longitudinal center line of the lamp arm
且燈的水平水平線應與地面平行, 擰緊後不應有歪斜.
6: The lamp head is firmly fixed
the adjustable lamp head should be adjusted to the correct position according to the design, and the lamp head wiring should comply with the regulations.
7: Tighten various nuts
and add gaskets and spring pads.
8: Pouring
put the embedded parts into the pit and pour cement. During the pouring process, pay attention to stabilize the embedded parts and ensure that the embedded parts are straight.
9: Fix the LED street light
After the foundation is dry, fix the bottom flange of the assembled LED路燈 with the embedded parts and tighten the screws.

Solar transformation of existing old lamp poles and street lights. Simple solar street lights can be used. Simple solar street lights combine solar panels, batteries, and lamps reasonably and effectively. You only need to fix the hoop behind the simple solar street light on the lamp pole to achieve solar lighting. Remove the old lamp pole and carry out the transformation.
Before the lamp pole is hoisted, the corresponding solar panels, solar panel brackets, lamp arms, lamps, lamp pole wiring, 等. should be installed in place on the ground. After the installation inspection is completed, the light pole is hoisted by a crane. After the hoisting is completed, a lighting test is carried out. After the test is completed, the light pole is adjusted. If secondary pre-embedding is required, secondary pre-embedding is carried out (the exposed bolts on the ground are covered with cement), and no surface treatment is required.
YUANNENGJI